Construction will be for the period from 14 September 2015 until 20 May 2016 on the 3rd phase of the Stockville Road upgrade.
- Stockville Road will be subject to daytime Stop & Go, with access to residents only, from 07h00 until 17h00 due to lane closures for the full duration from 14 September 2015 to 20 May 2016.
- Stockville Road will be completely closed to all traffic except residents from 21 September 2015 to 31 October 2015.
“Please be aware the Stockville Road will only be open to residents during the entire construction period of 14 September 2015 until 20 May 2016. If you usually use Stockville Road as a short cut to the N3 you will have to use the M13 or take Kassier Road to the N3. Local residents will be provided with a permit / gate pass” said Councillor Rick Crouch.
Should residents have any questions please contact; eThekwini Roads Department officials Sandile Manqele (031) 311-2732 or Steven Chetty (031) 311-2721